Culvert Replacement Project Updated

Culvert Replacement Project Updated

 Stone Pillar Road

The contractor (De Groot Inc.) will be replacing the two culverts on Stone Pillar Road on Monday and Tuesday of next week (August 14 & 15).  Traffic will NOT be able to get through on Stone Pillar when this work is being done.   If It rains and contractor cannot work, the schedule will get pushed back one day.

Caledonia Drive

The contractor will be replacing the culverts on Caledonia Drive and side road pipes at the intersections starting next week after they finish the work on Stone Pillar.  As the culverts are being replaced you will not be able to get through the work area during working hours.

Doris Lane

The culvert on the curve of Doris Lane will be replaced next week or the week after.  The work will take a day and the road will not be passable when they are doing the work. 

Scott Brosteau, PE, Mead & Hunt; Direct: 920-593-6860; Cell: 920-639-1386